Getting the Metrolink trams running again

August 25, 2009

By Steve Johnson

As we near the planned restart of tram operations on the Altrincham line the pressure is building in the delivery team. The guys replacing the overhead line equipment on the old British Rail infrastructure are pulling out all the stops trying to get everything finished on time, whilst in the city centre what feels like hundreds of orange clad bodies are feverishly trying to get the tracks and road surfaces in position ready for the trams to run.
 
To add to the stress, it is Manchester Pride this weekend and there are expected to be thousands of extra people in the city making moving materials and guys around even more torturous than usual.
 
There is a real will to get the work complete and it will not be for a lack of trying if it is not quite ready. I am sure trams will be running again on Tues 1st September.
 
Update 2nd Sept
Well I wasn’t quite right, but St Peters Station was back up and running as planned. Unfortunaley there have been a few problems down at the Altrincham end.

This post was written by Steve Johnson